The boiler house of OJSC “MMC “Norilsk Nickel”

The group of companies "NATEK" won the tender for the construction of boiler with capacity of 140 MW for the needs of OJSC "MMC" Norilsk Nickel", 1.4 bn. rubles worth.

The construction of boiler for Skalistaya mine is a large-scale project, implemented in special climate (permafrost) and logistic conditions (delivery of goods in the Norilsk industrial area is possible only by river way (in summer) or by the Northern Sea Route (in winter) and aircraft).

The boiler is designed to provide with heat supply the newly commissioned capacities of Skalistaya mine under conditions of deterioration of existing heat network from the main source of heat supply of Talnakh region - CHP-2 OJSC "NATEC".

In addition, the boiler will take over the functions of emergency heat supply for the customers of Talnakhskaya industrial site in the event of an accident at CHP-2.