“Severnaya” mini CHP

Location: Primorsky region, Russky Island

The electric power: 3.6 MW

The heat power: 12.6 MW (10.83 Gcal/h)

The basic equipment:

−    2 package duel-fuel (gas/diesel oil) gas-turbine units (GTU) OPRA DTG1,8/L of the firm OPRA (the Netherlands), the electric power of each GTU – 1800 kW, the heat power – 4.3 MW;

−    2 peak hot-water boilers “TERMOTECHNIC” ТТ 100 of the firm “ENTROROS” with the heat power of each – 2.0MW, with the multifuel burners GКР-140Н (gas/diesel oil) of the firm Oilon (Finland);

−    2 modular containerized diesel power plant GMC1400 with electric power 1000kW of the production GM (Russia).       

The site putting into commissioning: March, 2012

The main fuel of generating equipment of mini CHP is gas, the backup source is diesel oil.

The ability to work on two types of fuel increases the efficiency and reliability of the power layout of the facilities under construction on the Russky Island.

“Severnaya” mini CHP is intended to provide electricity and heat to the bulks of the Far Eastern Federal University and to the customers of Pospelovo settlement in the Russky Island.